Common Knowledge for Pump Applications: Starting, Operation, and Shutdown
Common Knowledge for Pump Applications: Startup
a) Before starting up, remove any debris left near the machine and clean the work area thoroughly.
(b) Before connecting the motor to the pump, verify that the motor’s rotation direction is correct and that the pump turns smoothly. (Alternatively, after filling the pump with water, check the motor’s rotation; never allow the pump to run dry.)
(c) Close the gate valve on the discharge pipeline.
(d) Fill the pump with water, or use a vacuum pump to prime it.
(e) Connect the power supply. Once the pump has reached its normal speed, gradually open the gate valve on the discharge line and adjust it to the desired operating conditions. With the gate valve on the discharge line closed, the pump must not be run continuously for more than 3 minutes.
Common Knowledge for Pump Applications: Operation
(a) During operation and running, carefully monitor the instrument readings, bearing temperature rise, packing leakage and its temperature rise, as well as pump vibration and unusual noises to ensure they are within normal limits. If any abnormalities are detected, address them promptly.
(b) The temperature difference between the bearing and the ambient temperature shall not exceed 40°C, and the bearing temperature rise shall not exceed 80°C.
(c) Packing leakage should be slight and uniform.
(d) The bearing oil level shall be maintained at the normal position; it must not be too high or too low. If the oil level is too low, lubricant should be replenished promptly.
(e) If the clearance at the mating interface between the seal ring and the impeller is excessively worn, the seal ring should be replaced with a new one (for new pumps, the radial clearance is approximately 0.15–0.25 mm).
(f) The pump should, whenever possible, operate near the performance point specified on its nameplate (e.g., flow rate, head), enabling it to run continuously within the optimal efficiency range and achieving maximum energy savings.
Common Knowledge for Pump Applications: Shutdown
(a) Gradually close the gate valve on the discharge pipeline and disconnect the power supply.
(b) After the pump has cooled, close all cooling and sealant lines.
(c) If the ambient temperature falls below 0°C, drain the water from the pump to prevent freezing and cracking.
(d) If the pump is to be out of service for an extended period, it should be disassembled, cleaned, lubricated, and properly packaged for storage.